Department · 05 · p.58
Letters from the Loadout — the FAQ, addressed.
A touring-industry FAQ in the form readers have always written it — letters from road managers, production managers, and lighting designers, with an editor response set in the body face. Five this issue; more in the bound annual at the bay.
The letters department exists because the questions we get on the dispatch line repeat. Rather than write a generic FAQ that fits no one, we publish the actual questions in their original form (lightly edited for length and brevity) with the answers we’ve given over the phone. Letters arrive at letters@briley-stage.example. We publish four to six per issue; the rest get a reply but not a print run.
From a tour manager · National country headliner · routed via Bridgestone · 14 May 2026
Hi Briley team — we’re routing through Nashville on 22 June and the venue (Bridgestone) said you’re the shop they recommend for the feeder. We’re a 14-truck package, 1,000 A draw on the lighting and audio rigs combined. How much lead time do you actually need? Our tour manager keeps booking us into venues with three weeks notice and that is making my life hard.
— A.
Three weeks is plenty for the work itself. Three days is the minimum for our side — the cable goes on the truck on the morning of, the gear is staged in the bay by the night before. What three weeks gives us is the AHJ walkthrough and the venue’s house electrician on the call sheet, both of which we will not skip. Our advance window is at least ten working days before doors for a venue we haven’t worked, and three days for a venue (Bridgestone, TPAC, Ryman) we have. Send the production manager the link to /advance/; we need stage plot, rider, gauge plan, and load-in window, and the rest is mechanics. Looking forward to it.
From a lighting designer · Touring repertory company · 28 Mar 2026
I’m working a touring rep that hits TPAC in late spring 2026. The venue has a 600 A panel feeding their dimmer rack. Our rig wants 28 channels of full-channel hits simultaneously during a specific scene change. Will their panel handle that, and if not what does that mean for us?
— G.
28 channels at full intensity is 95.2 A on a single phase if your fixture pack averages 410 W per channel, which is roughly an L-Acoustics audio rack’s worth of draw concentrated on one phase. The TPAC panel can handle that, but only if the circuits are distributed across the three phases rather than landed on the same leg. We did your show — see PRD-2026-055. The reroute took 78 minutes including LOTO, PPE on, the actual circuit moves, and the panel directory updates. If you’re working other venues with similar architecture, the question to ask in advance is which phase each dimmer channel lands on; the answer should be balanced within 15% across all three.
From a road manager · Festival production · 11 Feb 2026
We’re running an outdoor festival on a county fairground in May. There’s a 200 A drop the fairground manager says he can give us, but I’ve never actually verified that. How would you approach this if you were us? We’re going to want power for two stages, a couple of food trucks, and three trailer-mounted dressing rooms.
— J.
Don’t take the fairground manager’s word for the 200 A — get the utility’s inspector to confirm what’s actually at the meter, and ask the AHJ what permit modifications a 200 A temp drop will need. Two stages plus food trucks plus dressing rooms is more like 400 A peak under coincident load (we use a 0.7 coincidence factor on temporary services), so even if the 200 A is real, you’ll need a second tap or a paralleled gen bank. We carry two DCA-150s and a Cat XQ230 that can back-feed; that’s the configuration we ran at the South Main Street Festival last month. Send the site plan and we can put numbers to it. NEC Article 525 is the governing section; P-06 walks the procedure.
From a touring electrician · Country act, 12-truck · 22 Jan 2026
I’m new to the road side after eight years on the IBEW commercial side. The advance paperwork is killing me — there’s a different format for every venue. How do you keep it consistent across a multi-week tour?
— M.
The format we use is in the bound issue at the bay; send a SASE and we’ll mail you a sample. Short answer: one binder per tour, with tabs for advance (the stage plot and rider that came from the production manager), cable manifest (which we generate from the plot), daily log (Megger, GFCI trip-test, phase-rotation, ground-rod readings — one row per day per venue), and a venue-specific tab for any AHJ quirks. The format is patterned on USITT stage management practice and the StudioBinder call-sheet template, with the columns that don’t belong to electrical taken out. After three or four tours you’ll have your own version that fits your hand. Keep your daily log honest; it’s the only document that survives the season.
From a production designer · Independent film unit · 03 Jan 2026
We’re shooting a music documentary at a Nashville studio in March and the production needs more power than the studio service can supply. Two HMI 18K’s, a Skypanel package, and a base-camp tent for craft service and hair/makeup. Can you run a temp service for a five-day shoot?
— S.
Yes — that’s a P-06 with a film twist. Two HMI 18K’s pull 60 A each at 208 V single-phase; the Skypanel pack is ~10 A per fixture; base-camp adds another 80 A nominal. Total nameplate is around 240 A coincident; we’d size at 300 A continuous to account for inrush on the HMI ballasts. A single Cat XQ60 covers that comfortably and we can stage one on a graveled pad outside the studio if the property allows the noise. For five days the fuel logistics is one Mansfield delivery on Day 1 and one on Day 4, with quiet hours observed if the studio has neighbors. Send the production plan; we’ll quote.
Frequently asked questions, in shorter form
- Lead time
- Three working days inside Davidson County for any P-01 through P-05 scope. Ten working days for P-06 (festival temp), driven by AHJ permit windows.
- Insurance
- $2M general liability · $1M professional · $1M auto. Certificates available on request before contract execution.
- Service area
- Tennessee, Kentucky, North Alabama, North Mississippi, North Georgia, Arkansas, the Bootheel of Missouri, southern Indiana. We sub-contract or refer for anything outside.
- Residential
- Never. See /protocols/#not-us for the full list of work we refer out.
- Walk-through
- Mandatory before tie-in on every job. Walk-throughs are included in the booking; we will not energize a service without one.
- Card requirements
- ETCP Entertainment Electrician for protocols P-01 through P-06. ETCP Rigger-Arena additionally for P-04 (stage-rigging electrical). All card numbers and expirations available on request.
- Late-night dispatch
- 24-hour on-call line: 615 · 555 · 0418. We answer within 45 minutes for shows that are loaded in.
References & further reading
- ETCP — Entertainment Technician Certification Program
- USITT — production paperwork standards
- StudioBinder — call sheet anatomy (film world)
- IATSE — local 46 (Nashville)
- NFPA 70 — NEC, Article 525
- Mansfield Energy — regional fuel delivery
- ACORD — insurance certificate formats
- C.P. Rigging — Nashville rigging vendor
- MusicRow Magazine — Nashville touring industry coverage
- Metro Codes & Building Safety — Nashville AHJ